Policy: Procurement and Subcontracting: Difference between revisions

From Future Worlds Center Wiki
Jump to navigationJump to search
no edit summary
No edit summary
No edit summary
 
(One intermediate revision by the same user not shown)
Line 2: Line 2:
* A [[Project Coordinator]] may decide to subcontract a task related to a project without any further permission, provided this has been part of a contract already signed with a funding agency.
* A [[Project Coordinator]] may decide to subcontract a task related to a project without any further permission, provided this has been part of a contract already signed with a funding agency.
* A task can be subcontracted to a third-party without the need for tenders if the total amount €10,000 unless financial regulations of the relevant project instruct otherwise.
* A task can be subcontracted to a third-party without the need for tenders if the total amount €10,000 unless financial regulations of the relevant project instruct otherwise.
* In all other cases, the [[Project Coordinator]] is expected to request three tenders and also receive clearance from the [[Financial Officer]] and the [[Executive Director]].
* In all other cases, the [[Project Coordinator]] is expected to follow the organization's procurement policy, which demands requesting three tenders and also receiving clearance from the [[Financial Officer]] and the [[Executive Director]].